Machine identity, configuration and supply scope. An evidence register, document references and a clear missing-information list.
Maria Roboter / Engineering guide
A specification starts the conversation. Condition, process fit and the move to your plant define the questions that follow. Build a clear picture before you commit.
Maria Roboter GmbH Technical Team
Published 18 September 2026 · Updated 15 October 2026
A used paper machine review should establish equipment identity and supply scope, mechanical and electrical condition, process suitability, documentation quality, dismantling and transport needs, refurbishment requirements and the total restart cost framework. Each conclusion needs a clear evidence basis.
01 / Organise the evidence
Select the status that describes your current information in each domain. Use the result to prepare questions for your technical team or an agreed professional assessment.
Evidence received ≠ technically verified. Review each source for relevance, completeness and consistency with the actual machine.
02 / Review the complete project
Open each domain for practical checks and useful evidence. Apply the framework to the actual machine, its operating history and the requirements of the destination plant.
Decision rule: condition statements should be linked to inspection evidence, maintenance records or measurements. If evidence is unavailable, the point remains an open risk rather than an assumed fact.
Maintenance history, detailed photos, repairs, condition measurements and spare-parts records.
A machine can be mechanically usable and still require major automation investment. Electrical compatibility must therefore be priced before the purchase decision, not after delivery.
Motor and drive lists, electrical drawings, hardware inventory, software licences and control-system backups.
Important: indicative capacity is not a guarantee. It must be reconciled against furnish, grade, basis weight, operating history, utilities and the planned configuration at the destination mill.
Production records, grade and furnish data, basis-weight range, process flows and utility requirements.
Inspection while the equipment is still installed reduces uncertainty because interfaces, access and the relationship between main equipment and auxiliaries remain visible.
Layouts, supply boundaries, access information, lifting provisions and a component-marking plan.
The agreed Incoterm must match the actual scope. EXW, FCA and CIF allocate cost and responsibility differently and should not be treated as interchangeable quotations.
Component dimensions and weights, handling instructions, route survey and packing specifications.
A realistic budget should include more than the equipment purchase price:
The most useful comparison is total landed-and-restarted cost versus a technically equivalent new solution, including schedule and risk—not purchase price alone.
Condition findings, parts lists, repair scope and supplier quotations for proposed work.
The investment case should combine technical evidence with commercial assumptions:
Go/no-go logic: proceed only when critical technical fit is confirmed, unresolved risks are priced, and the buyer understands which performance points are documented, reported or still subject to verification.
Equipment offer, implementation quotations, restart budget, operating assumptions and contingencies.
Commercial and legal review should be completed by the buyer's qualified advisers. Technical review does not replace contract, tax, customs or legal due diligence.
Asset identifiers, itemised offer, inclusions and exclusions, inspection access and agreed responsibilities.
03 / Make the findings useful
Machine identity, configuration and supply scope. An evidence register, document references and a clear missing-information list.
Process fit against your product and capacity target, condition observations and a risk register distinguishing confirmed information from unresolved points.
Dismantling, packing and logistics assumptions, a preliminary refurbishment and total-project cost framework, and the next checks before commitment.
Direct answers
It is a structured review of machine identity, process fit, mechanical and electrical condition, documentation, relocation risk and total restart cost before purchase.
Yes, when possible. Installed inspection helps verify configuration, interfaces, access, visible condition and dismantling requirements before those relationships are lost.
Priority documents include machine lists, general arrangements, process flows, motor and drive lists, electrical drawings, automation backups, maintenance history, rebuild records, spare-parts lists and production data.
No. Inspection reduces uncertainty, but final performance depends on condition, furnish, grade, utilities, refurbishment, installation, commissioning and operating practice.
Project scope can include technical clarification, site inspection, dismantling planning, match-marking, export packing and international delivery, subject to agreed requirements.
No. The review builder records the document status you select. A professional assessment must examine the evidence, confirm its relevance to the actual equipment and identify any checks that remain open.
This guide structures an initial review. Maria Roboter can quote a document assessment, site inspection or relocation readiness assignment with defined checks and deliverables.
For internal project evaluation. Republishing or commercial reuse of the original content and design requires written permission. The review brief generated by the tool may be used for your project.
Discuss your equipment
Include the equipment or MR reference, listing link, intended product, furnish, target capacity and destination requirements. You can add the review brief above and attach the available documents.
We will use your details to respond and agree the assessment scope and quotation. Work begins under a separately agreed proposal. Privacy information and data requests.